NEW QUESTION 46
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

  • A. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
  • B. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
  • C. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.
  • D. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.

Answer: D

 

NEW QUESTION 47
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are
3 correct Answers to this question.

  • A. Cancel goods issue
  • B. Stock transfer posting
  • C. Generate delivery
  • D. Confirm production order
  • E. Generate purchase requisition

Answer: B,C,E

 

NEW QUESTION 48
You are using budgeting and active availability control. How can availability control be activated? Note:
There are 2 correct Answers to this question.

  • A. Automatic activation with the first actual posting
  • B. Automatic activation with budget assignment
  • C. Background activation (CJBV - Activate Availability Control)
  • D. Automatic activation with assignment to an investment program

Answer: B,C

 

NEW QUESTION 49
To which object can you assign a factory calendar?

  • A. Milestone
  • B. Relationship
  • C. Network header
  • D. Material component

Answer: C

 

NEW QUESTION 50
You are working with networks and WBS elements. Which of the following statements applies?

  • A. You can reassign an activity from one network to another.
  • B. You have to maintain a network profile in the project profile.
  • C. You can assign the network header to multiple WBS elements.
  • D. You have to activate the operative indicator Account Assignment Element for WBS elements with activities.

Answer: A,C

 

NEW QUESTION 51
Which objects can be used to specify settlement rules? Note: There are 2 correct Answers to this question.

  • A. Network header for activity-account-assigned networks
  • B. WBS elements
  • C. Standard WBS elements
  • D. Network activity for activity-account-assigned networks

Answer: A,B

 

NEW QUESTION 52
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?

  • A. Missing material availability
  • B. Missing authorizations to release material components
  • C. Missing reservations for material components
  • D. Missing budget for material components

Answer: B

 

NEW QUESTION 53
What functionality can you perform with activity elements?

  • A. Schedule WBS elements
  • B. Assign work centers and capacities
  • C. Assign material
  • D. Create relationships

Answer: D

 

NEW QUESTION 54
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.

  • A. Saving a goods receipt
  • B. Saving a supplier invoice
  • C. Saving a service entry sheet
  • D. Saving a purchase order

Answer: A,C

 

NEW QUESTION 55
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.

  • A. Shift activities backward or forward on the time axis where more capacities are available.
  • B. Maintain subordinate internal activity elements assigned to other work centers.
  • C. Increase the capacities of the work center in the project planning board.
  • D. Trigger automatic capacity leveling inside the project planning board.

Answer: A,D

 

NEW QUESTION 56
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?

  • A. Activity
  • B. Milestone
  • C. Activity element
  • D. Network header

Answer: A

 

NEW QUESTION 57
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?

  • A. Forward
  • B. Only capacity requirements
  • C. Backward
  • D. Current date

Answer: C

 

NEW QUESTION 58
Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.

  • A. In the project version
  • B. In the project definition of a standard WBS
  • C. In the project type
  • D. In the operative WBS element
  • E. In the project profile

Answer: B,D,E

 

NEW QUESTION 59
How can you grant individual authorization for WBS elements and networks?

  • A. Define a user status to lock the business transaction Update Project.
  • B. Set the system status to "Lock Master Data".
  • C. Activate access control lists (ACL) for the user master record.
  • D. Activate access control lists (ACL) for the project profile and the network profile.

Answer: D

 

NEW QUESTION 60
How can you update the degree of processing for an activity?

  • A. By using results analysis
  • B. By confirming the activity
  • C. By changing the activity
  • D. By scheduling the activity

Answer: B

 

NEW QUESTION 61
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.

  • A. Milestones
  • B. Project definition
  • C. Sales order items
  • D. WBS elements

Answer: C,D

 

NEW QUESTION 62
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.

  • A. Planned revenue can be transferred from a sales quotation.
  • B. Actual revenue is posted via a billing plan assigned to a WBS element.
  • C. Planned revenue requires a sales order assigned to a WBS element.
  • D. Actual revenue is posted via a billing document created from a sales order

Answer: A,D

 

NEW QUESTION 63
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.

  • A. Preliminary purchase requisition for WBS element
  • B. Purchase requisition and Reservation for WBS element
  • C. Planned order
  • D. Third-party order
  • E. Reservation for WBS element

Answer: A,B,E

 

NEW QUESTION 64
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?

  • A. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
  • B. Set up the requirement date manually as February 5.
  • C. Set up the requirement date aligned with the activity start date and an offset of 5 days.
  • D. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.

Answer: C

 

NEW QUESTION 65
......