Master 2021 Latest The Questions Professional Scrum Master and Pass PSM-II Real Exam!
Penetration testers simulate PSM-II exam PDF
How much Scrum PSM II: Professional Scrum Master II Exam Cost
The cost of the Scrum PSM II: Professional Scrum Master II Exam is USD 250. For more information related to exam price, please visit the official website at SCRUMstudy Website as the cost of exams may vary according to the region of the candidate.
NEW QUESTION 97
The Development Team has suggested to move the Daily Scrum to every other day instead of every day.
What is the most appropriate action for the Scrum Master to take?
- A. Have the Development Team members vote on which days the Daily Scrum should occur.
- B. Learn why the Development Team wants this, coach the team on why the Daily Scrum is important and work with them to improve the outcome of the Daily Scrum.
- C. Support the self-organizing team's decision.
Answer: B
Explanation:
The Scrum Master is responsible for promoting and supporting Scrum as defined in the Scrum Guide. Scrum Masters do this by helping everyone understand Scrum theory, practices, rules, and values.
NEW QUESTION 98
Doing your best and helping other Scrum Team members demonstrates which of the following?
- A. Maximizing utilization
- B. Value of Commitment
- C. Increased Revenue
- D. Increased Profit
- E. High Performance
Answer: B
Explanation:
People personally commit to achieving the goals of the Scrum Team by doing their best and helping others.
NEW QUESTION 99
What is the most appropriate action for the Scrum Master to take if the Product Owner is having difficulties managing the Product Backlog?
- A. Have the Development Team order the work instead of the Product Owner.
- B. Have the Product Owner order the items based on size, having the Development Team work on the smallest items first.
- C. Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize the flow of value.
- D. Delegate the work to the Assistant Product Owner.
- E. Delay the Sprint in order for the Product Owner to have enough time to prioritize the Product Backlog.
Answer: C
Explanation:
Explanation/Reference:
Explanation:
The Product Owner's primary concern is the flow of value reflected in the ordering of the Product Backlog.
NEW QUESTION 100
On a project where multiple Scrum Teams are working from the same Product Backlog, how should the work be distributed between teams?
- A. The Scrum Team with the highest capacity will pull items from the Product Backlog first.
- B. Each Scrum Team must have an equal amount of User Stories per Sprint.
- C. The Development Teams pull in work from a shared Product Backlog in agreement with the Product Owner and the other teams.
- D. The Product Owner separates the Product Backlog items for each team.
Answer: C
Explanation:
During Sprint Planning the number of items selected from the Product Backlog for the Sprint is solely up to the Development Team regardless of the number of Development Teams working from the same Product Backlog. Only the Development Team can assess what it can accomplish over the upcoming Sprint.
NEW QUESTION 101
During the implementation of an item in the Sprint Backlog, a conflict arises between team members about what work is needed to make the item 'done'. Some say it is a part of the Definition of Done and others say it isn't. Steven, the Scrum Master, observes a debate forming and members beginning to take sides.
What is the best action for Steven to take?
- A. Bring the Development Team members together and interpret the Definition of Done for them so that there are no future conflicts on interpretation.
- B. Immediately end the discussion before it becomes worse. Make the decision on what work is needed to make the item 'done' and teach the team about the importance of avoiding conflicts.
- C. Bring the Product Owner to the discussion and have him/her decide the work needed to make the item 'done.' It is the Product Owner's responsibility to manage the Development Team members.
- D. Facilitate a session with all members on the Scrum Team to help them resolve the conflict, refine the Definition of Done, and become effective again. Tell the team that conflicts are a natural occurrence and coach them on the value of resolving conflicts.
Answer: D
Explanation:
The Scrum Master is a servant-leader for the Scrum Team. The Scrum Master helps the Scrum Team understand which of their interactions are helpful and which are not. The Scrum Master helps everyone change these interactions to maximize the value created by the Scrum Team.
NEW QUESTION 102
After several Sprints, a key stakeholder starts using the product. The stakeholder is surprised by the slow performance and complains to the Product Owner. The Product Owner comes to the Scrum Master asking for advice.
What is the best action for a Scrum Master to take?
- A. Bring the concern to the testers in the Development Team and ask them to include performance testing.
- B. Wait until the next Sprint Retrospective as it is the most opportune time to modify the Definition of Done.
- C. Explain to the Product Owner that it's up to the Development Team to. decide on acceptable performance standards as they own the Definition of Done.
- D. Encourage the Product Owner to bring the performance concerns to the Development Team and work with them on how to improve performance, and ultimately have stronger Definition of Done.
Answer: D
Explanation:
The highest priority of agility is to satisfy the customer through early and continuous delivery of valuable software. Because the Development Team is the one doing the work and increments must meet performance standards, they can expand their Definition of Done to include more stringent criteria for higher quality.
NEW QUESTION 103
A new Product Owner is hired to work on an existing product that has ongoing for five Sprints. He/she is unsure about all of the responsibilities of a Product Owner. Which of these Product Owner's activities are defined in Scrum?
- A. Interacting with stakeholders and ensuring that the most valuable functionality is always produced first.
- B. Ensuring work is completed within scope and time.
- C. Writing User Stories.
- D. Describing features as Use Cases.
Answer: A
NEW QUESTION 104
Stakeholders are only allowed to meet with the Scrum Team at Sprint Review.
- A. False
- B. True
Answer: A
Explanation:
Getting feedback from Stakeholders is a crucial activity in Scrum. Working with stakeholders frequently ensures the team to focus on the right things to build. Although it is required to have Stakeholders at Sprint Review, they can also engage with the Scrum Team during Product Backlog Refinement, Sprint Planning or during the Sprint if the Scrum Team requires it.
NEW QUESTION 105
A PO (Product Owner) is essentially the same thing as a traditional PM (Project Manager).
- A. False
- B. True
Answer: A
Explanation:
Explanation
NEW QUESTION 106
How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint?
- A. Enough time for the last Increment to finish testing.
- B. Enough time for the Product Owner to prepare the Product Backlog for Sprint Planning.
- C. None. A new Sprint starts immediately following the conclusion of the previous Sprint.
- D. Maximum of one day for Sprints that are time-boxed to two weeks.
- E. All of the above are allowed.
Answer: C
Explanation:
Explanation/Reference:
NEW QUESTION 107
What action can the Scrum Master take to ensure communication between the Development Team and Product Owner is effective?
- A. Observe the communications between them and facilitate discussions if needed or by request.
- B. Teach the Product Owner to talk in terms of technology and technical requirements.
- C. Ensure all communication goes through the Scrum Master first.
- D. Translate the technologies used by the Development Team in order for the Product Owner to make decisions.
Answer: A
Explanation:
One of the primary responsibilities of a Scrum Master is the ability to facilitate regardless of the context or setting.
NEW QUESTION 108
Successful use of Scrum depends on how well people behave and act in ways that reflect the Scrum values. What can the value of openness affect?
- A. Team member happiness.
- B. Time to market.
- C. Trust from stakeholders.
- D. Collaboration efforts.
- E. All of the above.
- F. Level of product quality.
Answer: E
Explanation:
The Scrum Team and its stakeholders agree to be open about all the work and the challenges with performing the work.
NEW QUESTION 109
When does a Sprint end?
- A. When there is no work remaining in the Sprint Backlog.
- B. When the time-box expires.
- C. Immediately after the conclusion of the Sprint Review.
- D. It depends on the Product Owner.
Answer: B
NEW QUESTION 110
Which two statements are the most accurate in regards to scaling Scrum for large projects requiring multiple Scrum Teams? (Choose two.)
- A. Team members must work full time on a single Scrum Team.
- B. A person focusing on the Sprint Backlog of a single Scrum Team is often more productive than that same person working on multiple Scrum Teams at the same time.
- C. A well-structured Product Backlog can minimize and often eliminate Development Team members working on multiple Scrum Teams during a Sprint.
- D. Customizing the core Scrum framework is necessary to be successful with Scrum at large scale.
Answer: B,C
Explanation:
A person or team working on a single problem at a time is typically more effective than one that is working on multiple problems congruently as they can fully focus and dedicate their energy to resolving the problem before moving to the next. Having a well-structured Product Backlog can help minimize dependencies and increase focus for each team.
NEW QUESTION 111
The Development Team can cancel the Sprint:
- A. When the availability of the Product Owner is less than expected.
- B. When the Sprint Backlog is determined to be unachievable.
- C. When too many impediments occur.
- D. It can't. Only Product Owners can cancel Sprints.
- E. When the requirements for the work to be done become unclear or not understood.
Answer: D
NEW QUESTION 112
The Development Team discovers that it doesn't have the tools and infrastructure to make each selected Product Backlog item done.
What is the most appropriate action for the Scrum Master to take?
- A. Stop the Sprint and have the Development team work on the infrastructure before continuing.
- B. Encourage the Product Owner to accept partially done Increments and complete the work in the Hardening Sprint.
- C. Coach the Development Team to improve its skills, tools and infrastructure over time and establish a Definition of "Done" that is actually possible to achieve given the current circumstances.
Answer: C
Explanation:
The Scrum Master serves the Development Team by coaching it in self-organization and cross-functionality.
NEW QUESTION 113
Why is it important that there is only one Product Owner per product?
- A. It is clear who is accountable for the ultimate success of the product, the Development Team always knows who determines priorities, and it helps avoid barriers to effective communication and rapid decision- making.
- B. It isn't important as multiple Product Owners can easily share a single Product Backlog.
- C. The Scrum Master knows who will be his back-up whenever he is unavailable, it saves the organization time and money, and the Development Team knows who to request tasks from.
Answer: A
NEW QUESTION 114
A Development Team, that has remote team members, typically spends time before the Daily Scrum to setup the meeting rooms and conference calling equipment and tools in order to have their Daily Scrum.
How should the Scrum Master handle this situation?
- A. Inform management and ask them to solve it.
- B. Setup the meeting and tell the Development Team that is how it will be done.
- C. Ask the Development Team members to alternate who is responsible for meeting setup.
- D. Allow the Development Team to self-manage and decide for itself what to do.
Answer: D
Explanation:
As a self-organized team, they will decide for themselves how to best manage communication between team members. The Scrum Master will only take action if requested OR if he/she observes that there is a potential problem.
NEW QUESTION 115
What should a Development Team do with non-functional requirements?
- A. They will be addressed in the Integration Sprints.
- B. Assign them to the technical leads on the team.
- C. Ensure they are addressed in every Increment.
- D. Add them to a separate non-functional requirements list.
Answer: C
Explanation:
Non-functional requirements should be worked on alongside functional development.
NEW QUESTION 116
An organization has just hired you as a new Scrum Master to help them transition their teams from their current traditional process to Scrum. The teams are currently structured to specialize in a single function. This is also known as component teams where a team would only address a single layer (i.e. design, frontend, backend, database, testing, etc.). You've introduced the concept of cross-functional teams where all the skills needed to produce business functionality, from end to end, are inside of a single team.
What should you keep in mind when transitioning from siloed teams to cross-functional teams? (Choose two.)
- A. It is easier to compare the performance between cross-functional teams in order to identify to which teams to assign tasks and which teams need additional coaching.
- B. Without feature teams, you cannot do Scrum. Postpone Scrum adoption until the teams are reorganized in feature teams.
- C. Newly formed teams will need time to stabilize before reaching their peak performance. During the initial stages of forming, performance will suffer and productivity may be low, although even then delivery of business value is still likely to increase.
- D. People from the different layers and components will need time to become accustomed to working and delivering unified functionality together as one Scrum Team thus productivity may suffer.
Answer: C,D
Explanation:
Forming a team takes time, and members often go through recognizable stages as they change from being a collection of strangers to a united group with common goals. Bruce Tuckman's Forming, Storming, Norming, and Performing model describes these stages. When you understand it, you can help your new team become effective more quickly.
NEW QUESTION 117
......
How to Prepare For Scrum PSM II: Professional Scrum Master II Exam
Preparation Guide for Scrum PSM II: Professional Scrum Master II Exam
Introduction
SCRUMstudy is the national Scrum and Agile certification accreditation body. SCRUMstudy provides education, training, resources, and certifications to practitioners of Scrum and agile. Authorized Training Providers (A.T.P.s), being the biggest collaborator network of SCRUMstudy, provides a platform to deliver training and certifications.
According to SCRUMstudy, Scrum Master Certified professionals are facilitators who ensure that the Scrum Team has an atmosphere conducive to the successful completion of the project. The Scrum Master acts as the guide, facilitator, and teaches Scrum activities to all participants in the project; eliminates challenges for the team; and, ensures the follow-up of Scrum processes.
The PSM II exam has the aim to verify that the applicants have acquired the requisite knowledge of SCRUM application in SCRUM adaptation projects to a particular scenario. Candidates, with powerful agile practices learned, will be acknowledged as part of an elite group of professionals from Scrum who provide experience well beyond what a traditional project manager might contribute.
This guide provides a detailed overview of the Scrum Master Certified PSM II certification including all sorts of PSM II dumps, the exam format, topics covered, exam difficulty and PSM II practice exams, and the target audience profile.
How to study the Scrum PSM II: Professional Scrum Master II Exam
Several websites, including the official certification website SCRUMstudy, provide online learning and preparation for the exam. Two modes of learning are available i.e. Instructor-led and Online learning. Registrations for both modes can be done via the official website. Online courses for Scrum Master are available at Udemy, learn, and Encertify. Recorded videos of all course content are available as well as live classes and web conferences. E-Books and other reference study material can be found and downloaded from the SCRUMstudy website. All links are provided in the references section at the end of this document.