Scrum PAL-I or Professional Agile Leadership (PAL I) exam is an industry-recognized certification that is designed to assess the knowledge and skills of professionals who are involved in leading Agile practices in their organizations. The PAL I exam is based on the Scrum framework, which is a popular Agile methodology used for software development projects. Professional Agile Leadership (PAL I) certification is offered by Scrum.org, which is a leading global provider of Agile training and certification.
NEW QUESTION # 83
What should a Scrum Team do if the size of the team becomes too large?
- A. They should work with fewer Developers
- B. Nothing
- C. They should consider reorganizing into multiple cohesive Scrum Teams
- D. They must reorganize into multiple Scrum Teams
Answer: C
NEW QUESTION # 84
What is the purpose of looking at Unrealized Value?
- A. Estimate when the whole product will be finished
- B. Analyze who missed providing the expected experience
- C. Detect the flaws between the current experience of the users and the experience that they would like to have to fix it as soon as possible
- D. Detect an opportunity because of a gap between the current experience of the users and the experience that they would like to have
Answer: D
NEW QUESTION # 85
Which of the following expresses the organization's ability to quickly deliver new capabilities, services, or products?
- A. Time to Market.
- B. Current Value.
- C. Unrealized Value.
- D. Delivery Time.
- E. Ability to Innovate.
Answer: A
NEW QUESTION # 86
Which of the following Key Value Measures (KVMs) would be useful to understand and improve the Ability to Innovate? Select three answers
- A. Technical Debt
- B. Time Spent Context-Switching
- C. Time Spent Merging Code Between Branches
- D. Lead Time for Changes
- E. Time to Restore Service
- F. Release Frequency
Answer: A,B,C
NEW QUESTION # 87
You are interviewing a candidate to work as a Scrum Master in your company, you ask the candidate to briefly explain "Scrum".
Which of the following responses would you expect? Select four answers.
- A. Scrum is founded on lean thinking.
- B. Scrum is a collection is of best practices for building products.
- C. Scrum is a lightweight framework that helps people, teams and organizations generate value through adaptive solutions for complex problems.
- D. Different processes, techniques and methods can be employed within the framework.
- E. Scrum is an agile method that can only be used to develop software.
- F. Scrum is founded on empiricism.
Answer: A,C,D,F
NEW QUESTION # 88
Which sentences would you use to describe what a Product is? Select four answers
- A. Efficient
- B. It has a clear boundary
- C. It is a vehicle to deliver value
- D. It has well-defined users
- E. It has known stakeholders
- F. Software
Answer: B,C,D,E
NEW QUESTION # 89
A company needs to form four Scrum Teams. Team members should be spread across the teams to maintain high utilization of resources, be able to respond quickly, and remain productive when impediments occur.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 90
SportsTech is a company that has offices and employees around the world. Because they need to build teams with Developers from multiple locations, they cannot implement Scrum as Scrum recommends that all Developers should be co-located.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 91
Which of the following Key Value Measures (KVMs) would be useful to understand and improve the Current Value? Select three answers
- A. Customer or User Satisfaction Gap
- B. Customer Satisfaction
- C. Employee Satisfaction
- D. Market Share
- E. Release Frequency
- F. Customer Usage Index
Answer: B,C,F
NEW QUESTION # 92
Developers may meet more than once throughout the day for detailed discussions about adapting or re-planning the rest of the Sprint's work.
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 93
An international bank has a large structure with several levels of management. (Directors, many managers, Delivery Managers, Product Managers, Program Managers, Project Managers, CTO, CTO, etc.). The company has just hired four project managers and a director of operations. This company should not implement Scrum since a large management team does not contribute to the implementation of Scrum and agile methodologies would not benefit the company.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 94
The Agile Manifesto values more comprehensive documentation over working software.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 95
A member of a Scrum Team is interested in understanding the organization's ability to deliver value. She asks if he can explain what the Time to Market Key Value Area (T2M) can reveal.
What would you answer?
- A. The average time required to perform a release.
- B. The organization's ability to quickly deliver new capabilities, services, or products
- C. How quickly the organization can develop Products.
- D. The average velocity across all Scrum Teams in the organization.
Answer: B
NEW QUESTION # 96
As an Agile Leader, your most important responsibility is to set the product goals for the team and holding everyone to embody their responsibilities for meeting such goals.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 97
When does the Sprint end?
- A. In one month
- B. in two weeks
- C. When all the items are finished
- D. When the timebox expires.
- E. When the timebox expires. If all the items are finished, the Sprint can end before the timebox expires
- F. When the increment is ready
Answer: D
NEW QUESTION # 98
Reaching strategic goals requires experimenting, inspecting, and adapting
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 99
An organization wants to implement Scrum for its 5 teams developing software. HR has hired 5 Scrum Masters to assign one Scrum Master to each team that will guide and support the implementation of Scrum. To make the transition successful, the Scrum Masters agreed to shield the Scrum Teams from change and uncertainty from those outside the team who are not familiar with Agile.
As an Agile Leader, what would you say?
- A. The Product Owner should shield Scrum Teams from change and uncertainty.
- B. The Scrum Masters should shield recently formed Scrum Teams from change and uncertainty.
- C. The Scrum Masters should shield Scrum Teams with a low agile maturity level from change and uncertainty.
- D. The Scrum Masters should shield Scrum Teams from change and uncertainty.
- E. Scrum Masters should help Scrum Teams deal with and embrace change and uncertainty.
Answer: E
NEW QUESTION # 100
After Sprint 6, Developers say they need to complete the software architecture before they can begin working on the functional requirements.
As a Scrum Master, what is the most appropriate action you can take?
- A. Stop the ongoing Sprint and focus on completing the architecture first.
- B. Consider the architecture as technical debt and only focus on the functionality which needs to be built.
- C. The Scrum Master should ask the Developers to resolve this issue themselves.
- D. Coach the Developers that the architecture does not need to be perfect.
Answer: D
NEW QUESTION # 101
You work in a company as a Director of Product Delivery. A Scrum Team request to meet you because they need four more Developers. They think the workload is too high and they were working overtime to meet the Sprint Goals and deadlines. The need for additional Developers seems reasonable. As a part of Product Delivery, What you should do?
- A. You should interview candidates and select Developers for the team.
- B. Let the Scrum Team interview the candidates but you take the final hiring decision.
- C. Hire external Developers.
- D. Ask the technical recruiter to hire additional team members.
- E. The team is self-managing and must learn to manage existing resources efficiently.
- F. Support the Scrum Team with appropriate resources within the budgetary boundaries. You should allow them to hire additional Developers.
Answer: F
NEW QUESTION # 102
Ali is an Agile Leader managing five Scrum Teams. Ali delegates responsibilities depending on the maturity level of each team and team members. Is it a good idea to delegate responsibilities according to the maturity of the team even if it takes longer?
- A. NO
- B. YES
Answer: B
NEW QUESTION # 103
All the Product Backlog Items selected during the Sprint Planning and added to the Sprint Backlog must be done by the end of the Sprint
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 104
At least one representative of the Agile Managers should attend the Scrum Events of the Scrum Teams to make sure they are going as expected.
- A. TRUE
- B. FALSE
Answer: B