[2022] Pass EXIN ASM Test Practice Test Questions Exam Dumps
Verified ASM dumps Q&As - ASM dumps with Correct Answers
NEW QUESTION 23
Company ABC always works in the following way: The business chooses a set of requirements that it believes will add business value. It communicates the requirements to the IT organization. The IT organization responds back with a plan and estimates of cost and schedule. The business agrees to that plan. The IT organization executes the plan and delivers a product to the business.
What type of framework is company ABC following?
- A. DevOps
- B. Waterfall
- C. DSDM
- D. Lean
Answer: C
NEW QUESTION 24
The Product Owner informs the team that the release will be date-driven.
What kind of buffer for uncertainty is most important to use in this type of release?
- A. Feature buffer
- B. Schedule buffer
- C. Budget buffer
- D. Padding buffer
Answer: B
Explanation:
Explanation/Reference:
Explanation: In projects where time is of the essence, a schedule buffer can be implemented.
Reference: https://www.productbookshelf.com/2012/09/agile-estimating-and-planning/
NEW QUESTION 25
What is one of the most difficult challenges you face when transitioning your software development team to Scrum?
- A. Introducing certain technical practices
- B. Too rapid improvements are possible
- C. Team members may already have their hands full
Answer: C
NEW QUESTION 26
A Scrum Team has agreed on the following definition of Potentially Shippable:
Potentially Shippable increments must be tested and must meet the Conditions of Satisfaction provided by the Product Owner.
Why is it important to include 'tested' in the definition of what is Potentially Shippable?
- A. Increments that have passed these tests will be sent out.
- B. Increments are not 'Done' without testing for bugs.
- C. The increments must be tested to be cohesive.
- D. Testing shows how well the increments are integrated.
Answer: B
NEW QUESTION 27
A Scrum Team is supposed to deliver potentially snippable software at the end of each Sprint. During the last Sprint the Team did not deliver a potentially shippable increment.
The correct question to ask is: "What can we do to make sure we do better in the next Sprint?" Who is responsible for making sure this question asked?
- A. The Scrum Master
- B. The Development Team
- C. The Product Owner
- D. The Project Manager
Answer: A
NEW QUESTION 28
What is one of the risks if the Scrum Master is also a programmer on the team?
- A. The Scrum Master tries to push through changes to the process.
- B. The Scrum Master does not have the required people skills.
- C. The Scrum Master cannot stay away from critical path activities.
Answer: A
NEW QUESTION 29
What is the difference between NPV and IRR?
A: NPV is a measure of how much money a project can be expected to return in future value.
IRR is a measure of how quickly the money invested in the project will decrease in value.
B: NPV is a measure of how much money a project can be expected to return in today's present value.
IRR is a measure of how quickly the money invested in the project will increase in value.
C: IRR is a measure of how much money a project can be expected to return in future value.
NPV is a measure of how quickly the money invested in the project will decrease in value.
D: IRR is a measure of how much money a project can be expected to return in today's present value.
NPV is a measure of how quickly the money invested in the project will increase in value.
- A. Option A
- B. Option C
- C. Option B
- D. Option D
Answer: D
NEW QUESTION 30
The ability for a Scrum Team to self-organize around the goals of a project is fundamental to all Agile methodologies.
Why is a Scrum Team a self-organized team?
- A. Because it helps the Scrum Team to make their own decisions in the project
- B. So that the Scrum Team commits to their work and feels responsible
- C. To ensure that decisions are made by a collective instead of an individual
Answer: A
NEW QUESTION 31
The Product Owner informs the team that the release will be date-driven.
What kind of buffer for uncertainty is most important to use in this type of release?
- A. Feature buffer
- B. Schedule buffer
- C. Budget buffer
- D. Padding buffer
Answer: B
Explanation:
Explanation
In projects where time is of the essence, a schedule buffer can be implemented.
NEW QUESTION 32
Your organization found that the Product Owner is consistently under more pressure than the developments and other participants in the project.
What is common solution for that?
- A. Compiling a list with Product Owner tasks
- B. Rotating the Scrum Master role
- C. Using a Product Owner team
Answer: A
NEW QUESTION 33
As items are developed and removed from the top of the Product Backlog, the Product Backlog iceberg develops a flat spot at the top and loses its shape.
What would be a necessary measure to counter this effect?
- A. Using an improvement Backlog
- B. Prioritizing the Product Backlog
- C. Grooming the Product Backlog
- D. Creating a chart of the number of Product Backlog Items
Answer: C
NEW QUESTION 34
What is the recommended way of removing the resistance presented by skeptics?
- A. Fire them
- B. Reiterate and reinforce the commitment
- C. Appoint a champion skeptic
- D. Move them
Answer: C
NEW QUESTION 35
You are a project manager for a midsize software company, which still uses the Waterfall model. Your customer wants a new software project.
When should you consider the use of Agile?
- A. There are almost no ambiguous requirements.
- B. The scope lacks specificity and is unlikely to remain stable.
- C. The product definition is stable and will not change.
- D. The user technology to be developed is understood.
Answer: B
NEW QUESTION 36
During a Sprint Planning, a team has picked three User Stories:
Story 1 - 5 Story Points
Story 2 - 8 Story Points
Story 3 - 3 Story Points
At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these.
The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.
What is the Velocity of this team?
- A. Insufficient information given - it depends on % completion of Story 2
- B. 16 points
- C. 12 points
- D. 8 points
Answer: D
NEW QUESTION 37
A Scrum Master is teaching Agile estimation techniques using Story Points to a new team. A more experienced member of the team argues that:
An estimate expressed in Story Points is useful for a shorter period of time than an estimate in Ideal Days.
Is this true and what is the reason?
- A. No, because Story Points are more robust against changes in the work-environment.
- B. No, because estimating with Story Points is usually faster than with Ideal Days.
- C. Yes, because Story Points are only a relative measure and Ideal Days are not.
- D. Yes, because Ideal Days allow for a buffer and help to maintain the estimate.
Answer: A
NEW QUESTION 38
A Scrum Team suggests to have a project with 3 Sprints of 2 weeks, while the customer suggests 1 Sprint of 6 weeks.
What is the greatest advantage of having 3 Sprints of 2 weeks?
- A. The customer has to invest fewer time.
- B. The team can inspect and adapt 2 times.
- C. The team delivers more Story Points.
Answer: C
NEW QUESTION 39
Your company has discovered that it takes more than high quality, low cost, and differentiation to excel. It also takes speed and flexibility. This calls for a different approach: you are aware that the current process is not delivering acceptable results.
What would be the next activity after becoming aware?
- A. Transfer of the implications of using Scrum throughout the company
- B. Ability to succeed with Scrum
- C. Promotion of Scrum through sharing experiences so that we remember and others can see our successes
- D. Desire to adopt Scrum as a way to address current problems
Answer: C
NEW QUESTION 40
......
The benefit in Obtaining the ASM Exam Certification
- When Candidates applying for a job or looking to promotion in their current position, an EXIN Agile Scrum Master Certification in the field in which Candidates are applying will put you at the top of the list and make them a desirable candidate for employers.
- Candidates will get in-depth knowledge by completing the courses along with the access to revision materials for 6 months upon completion means they will have a wider skill set when it comes to the various technologies and systems than an uncertified professional. Certified Professional in this particular skill set is 74% more efficient when it comes to completing their tasks in a timely well-executed manner.
- Becoming EXIN Agile Scrum Master means one thing you are worth more to the company and therefore more to yourself in the form of an upgraded pay package. On average, an EXIN Agile Scrum Master member of staff is estimated to be worth 30% more to a company than their uncertified professionals.
- After completion of EXIN Agile Scrum Master Candidates receive official confirmation from Exin that you are now fully certified in their chosen field. This can be now added to their CV, cover letters and job applications.
- Organization owners invest a lot in their employees when it comes to their training with the goal of making them quicker, more efficient, and more knowledgeable about their role. Certified Professional will reduce the time he spends on tasks, meaning he can get more done this could help reduce company downtime when repairing faults on a system or fixing hardware problems.
ASM certification guide Q&A from Training Expert Exam4PDF: https://www.exam4pdf.com/ASM-dumps-torrent.html
The Best Exin Certification Study Guide for the ASM Exam: https://drive.google.com/open?id=1R_80FYanwiKbuLAZvmSyD0cJt3CtZICB