NEW QUESTION 24
During a Sprint Planning, a team has picked three User Stories:
Story 1 - 5 Story Points
Story 2 - 8 Story Points
Story 3 - 3 Story Points
At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these.
The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.
What is the Velocity of this team?
- A. 16 points
- B. 12 points
- C. 8 points
- D. Insufficient information given - it depends on % completion of Story 2
Answer: C
NEW QUESTION 25
What is the difference between NPV and IRR?
A: NPV is a measure of how much money a project can be expected to return in future value.
IRR is a measure of how quickly the money invested in the project will decrease in value.
B: NPV is a measure of how much money a project can be expected to return in today's present value.
IRR is a measure of how quickly the money invested in the project will increase in value.
C: IRR is a measure of how much money a project can be expected to return in future value.
NPV is a measure of how quickly the money invested in the project will decrease in value.
D: IRR is a measure of how much money a project can be expected to return in today's present value.
NPV is a measure of how quickly the money invested in the project will increase in value.
- A. Option A
- B. Option D
- C. Option B
- D. Option C
Answer: B
NEW QUESTION 26
A company is already using Scrum very successfully within the development department. While highly effective Scrum Teams deliver new software increments quickly, these increments are not being delivered fast enough to customers. Releases happen once every 3 months and it takes too much effort to make sure that the releases go smoothly.
What type of framework should this company try to establish?
- A. DSDM
- B. Lean
- C. DevOps
- D. Waterfall
Answer: C
NEW QUESTION 27
Company X-AppGo is very interested in getting the benefits of both the ITIL Framework and the Agile principles. They want to establish a disciplined service based approach, while reducing lead team in releasing application enhancements and improvements to their customer base.
Based on the above scenario, which would be the integrating Agile into the ITIL Framework?
- A. Service Transition and Service Operation
- B. Service Strategy and Service Design
- C. Service Design and Service Transition
- D. Service Strategy and Service Operation
Answer: A
NEW QUESTION 28
How can pair programming help with adopting Agile?
- A. It helps recognizing who wrote which code
- B. It is beneficial to knowledge transfer
- C. It makes development faster and cheaper
Answer: A
NEW QUESTION 29
As items are developed and removed from the top of the Product Backlog, the Product Backlog iceberg develops a flat spot at the top and loses its shape.
What would be a necessary measure to counter this effect?
- A. Using an improvement Backlog
- B. Creating a chart of the number of Product Backlog Items
- C. Grooming the Product Backlog
- D. Prioritizing the Product Backlog
Answer: C
NEW QUESTION 30
Company ABC always works in the following way: The business chooses a set of requirements that it believes will add business value. It communicates the requirements to the IT organization. The IT organization responds back with a plan and estimates of cost and schedule. The business agrees to that plan. The IT organization executes the plan and delivers a product to the business.
What type of framework is company ABC following?
- A. DevOps
- B. Lean
- C. Waterfall
- D. DSDM
Answer: D
NEW QUESTION 31
During a Sprint Planning, a team has picked three User Stories:
Story 1 - 5 Story Points
Story 2 - 8 Story Points
Story 3 - 3 Story Points
At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these. The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.
What is the Velocity of this team?
- A. 16 points
- B. 12 points
- C. 8 points
- D. Insufficient information given - it depends on % completion of Story 2
Answer: C
NEW QUESTION 32
The Product Owner informs the team that the release will be date-driven.
What kind of buffer for uncertainty is most important to use in this type of release?
- A. Feature buffer
- B. Budget buffer
- C. Schedule buffer
- D. Padding buffer
Answer: C
Explanation:
Explanation
In projects where time is of the essence, a schedule buffer can be implemented.
NEW QUESTION 33
A Scrum Master is teaching Agile estimation techniques using Story Points to a new team. A more experienced member of the team argues that:
An estimate expressed in Story Points is useful for a shorter period of time than an estimate in Ideal Days.
Is this true and what is the reason?
- A. Yes, because Ideal Days allow for a buffer and help to maintain the estimate.
- B. No, because estimating with Story Points is usually faster than with Ideal Days.
- C. Yes, because Story Points are only a relative measure and Ideal Days are not.
- D. No, because Story Points are more robust against changes in the work-environment.
Answer: D
NEW QUESTION 34
The Product Owner informs the team that the release will be date-driven.
What kind of buffer for uncertainty is most important to use in this type of release?
- A. Feature buffer
- B. Budget buffer
- C. Schedule buffer
- D. Padding buffer
Answer: C
Explanation:
Explanation/Reference:
Explanation: In projects where time is of the essence, a schedule buffer can be implemented.
Reference: https://www.productbookshelf.com/2012/09/agile-estimating-and-planning/
NEW QUESTION 35
What is one of the risks if the Scrum Master is also a programmer on the team?
- A. The Scrum Master cannot stay away from critical path activities.
- B. The Scrum Master tries to push through changes to the process.
- C. The Scrum Master does not have the required people skills.
Answer: B
NEW QUESTION 36
What is one of the most difficult challenges you face when transitioning your software development team to Scrum?
- A. Team members may already have their hands full
- B. Too rapid improvements are possible
- C. Introducing certain technical practices
Answer: A
NEW QUESTION 37
You are a project manager for a midsize software company, which still uses the Waterfall model. Your customer wants a new software project.
When should you consider the use of Agile?
- A. The scope lacks specificity and is unlikely to remain stable.
- B. The user technology to be developed is understood.
- C. There are almost no ambiguous requirements.
- D. The product definition is stable and will not change.
Answer: A
NEW QUESTION 38
A team finds bugs in a feature.
What is the best action to take?
- A. Create a task "Correct bugs" and estimate it.
- B. Create a task "Correct bugs" and let the Product Owner prioritize it.
- C. Create a User Story "As a client I want a zero defect product" and let the Product Owner prioritize it.
- D. Create a User Story "As a client I want a zero defect product" and estimate it.
Answer: A
NEW QUESTION 39
A large company of more than 400 people changes from the Waterfall to the Agile framework. The company uses the approach of applying Scrum to all projects in the organization using an all-in scenario. The leaders are reluctant to fully commit to Scrum and there are no experienced Scrum Masters available within the organization yet. Six months later, Scrum has failed in the company. Many different applications of Scrum have been tried with varying degrees of success. The company gives up and returns to the Waterfall approach.
What is the most likely reason that the transition did not work?
- A. The company was too large to transition easily. A successful pilot project should have been done first, to be able to copy from.
- B. There was no public display of Agility and, therefore, customers kept asking for Waterfall projects. The company gave up too early.
- C. The change to Agile was not disruptive enough to provoke a real change and there was not enough commitment to keeping the new process.
- D. Scrum was not properly promoted as a best practice and the best way to solve the problems of the organization which created a big risk.
Answer: A
NEW QUESTION 40
Which information Radiator can the team use best during the Sprint to track the work?
- A. Task board
- B. Product Backlog
- C. Gantt chart
- D. Release Burn Up
Answer: A
NEW QUESTION 41
Which Scrum meeting helps an organization become engaged in continuous process improvement?
- A. The Release Kickoff meeting
- B. The Sprint Retrospective meeting
- C. The Rolling Lookahead Planning meeting
- D. The Sprint Planning meeting
Answer: B
NEW QUESTION 42
Why is a Product Owner not allowed to define the workload of the Development Team for a new Sprint?
- A. This conflicts with the principle of Self-Management of the Development Team.
- B. The Scrum Master is responsible for the velocity of the Development Team.
- C. The Scrum Master and the Product Owner must agree on the workload of the Development Team.
- D. The Product Owner does not know the velocity of the Development Team.
Answer: A
NEW QUESTION 43
......
EXIN Practice Test Engine with ASM Questions: https://drive.google.com/open?id=1BkX6W3ydHPeUS3Nufqd5JdwOfI2bGurh
Guaranteed Success with Valid EXIN ASM Dumps: https://www.exam4pdf.com/ASM-dumps-torrent.html